2010 Beach Nourishment
USACE dredged the Merrimack River and placed over 220,000 cubic yards in front of 26 homes from Center Island going North Our first project was …
South & North Jetty Repairs 2012-5
The North & South jetties had last been repaired by the USACE @1970. By 2011, both jetties were structurally compromised creating navigational risks and risks …
Sand Placement and Dune Grass Planting at Reservation Terrace 2018-9
Worked with local residents to raise funds and get approvals to nourish the eroding dunes and plant dunegrass.
Stone placement South of Center Island 2014
After 6 homes were lost to erosion in 2013, homeowners South of the Center Island groin installed riprap in an attempt to fortify the dune. …
Hay Bales Wrapped in Sand Fencing 2011
Worked with local Conservation Agents in Newburyport & Newbury on this innovative and “permittable” approach to dune fortification.
Geotube sandbags at Center Island 2009
Along with the MRBA helped get approvals to install protection for 9 homes pending the 2010 USACE Beach Nourishment.
Fiscal Agent for Project to Fund and Place AED’s